Palmer Drive Parking Structure

Photos

Photos - September 2002      

Click on image to enlarge (640 x 480, 68K)

Windows Installed on the west elevation of the LSI Building. September 2002

Click on image to enlarge (640 x 480, 49K)

Cooling Towers Delivered to the Commons Building. September 2002

Click on image to enlarge (640 x 480, 56K)

868’ level bridge to the Fletcher deck. September 2002

Click on image to enlarge (640 x 480, 58K)

LSI Loading Dock (Area 3). September 2002

       

Photos - August 2002

     

Click on image to enlarge (640 x 480, 65K)

Stone placement on the west elevation of the LSI Building August 2002

Click on image to enlarge (640 x 480, 67K)

Hoist installed on south side of Commons Building August 2002

Click on image to enlarge (640 x 480, 67K)

Excavation for the LSI loading dock August 2002

Click on image to enlarge (640 x 480,63 67K)

Shoring and fromwork for the Fletcher bridge connector August 2002

       
Photos - July 2002      

Click on image to enlarge (640 x 480, 65K)

Stone placement on the LSI Building July 2002

Click on image to enlarge (640 x 480, 61K)

Parking Structure July 2002

Click on image to enlarge (640 x 480, 68K)

Level 1 raised concrete floor in the Commons Building ready for concrete July 2002

Click on image to enlarge (640 x 480,63 K)

Auger cast piles for pedestrian bridge being installed July 2002  

       
Photos - June 2002      

Click on image to enlarge (640 x 480, 71K)

Installation of chillers in Commons Building June 2002

Click on image to enlarge (640 x 480, 56K)

Toilet room plumbing in LSI Building June 2002

Click on image to enlarge (640 x 480, 71K)

Lecture hall, prior to concrete, in the Commons Building June 2002

Click on image to enlarge (640 x 480, 60K)

Site preparation for LSI loading dock June 2002

       
Photos - May 2002      

Click on image to enlarge (640 x 480, 75K)

NUBS demolition. May 2002

Click on image to enlarge (640 x 480, 59K)

Completion of structural steel for Commons Building. May 2002

Click on image to enlarge (640 x 480, 66K)

Post tension wires on Parking Structure. May 2002

Click on image to enlarge (640 x 480, 70K)

LSI mockup. May 2002

       
Photos - April 2002      

Click on image to enlarge (640 x 480, 58K)

Permanent Utility Tunnel Tie-in. April 2002

Click on image to enlarge (640 x 480, 70K)

Structural steel erection of the Commons Building. April 2002

Click on image to enlarge (640 x 480,61K)

Concrete poured on west side of the Parking Structure. April 2002

Click on image to enlarge (640 x 480, 54K)

Masonry block on north and west sides of LSI. April 2002

       
Photos - March 2002      


Click on image to enlarge (640 x 480, 58K)

Electrical and toilet rooms framed on level 6. March 2002

Click on image to enlarge (640 x 480, 70K)

Structural steel and decking continue on the Commons Building. March 2002

Click on image to enlarge (640 x 480,61K)

Formwork continues on the east side of the Parking Structure. March 2002  

Click on image to enlarge (640 x 480, 54K)

Masonry block installed on the LSI construction mock-up. March 2002

       
Photos - February 2002      

Click on image to enlarge (640 x 480, 67K)

Air handling units delivered to the LSI Building. February 2002

Click on image to enlarge (640 x 480, 68K)

Decking continues on the west side of the Parking Structure. February 2002

Click on image to enlarge (640 x 480,78K)

Structural steel is erected in the Commons Building. February 2002

Click on image to enlarge (640 x 480, 59K)

Formwork on the east side of the Parking Structure. February 2002

       
Photos - January 2002      

Click on image to enlarge (640 x 480, 62K)

Commons Building Structural Steel is erected. January 2002

Click on image to enlarge (640 x 480, 54K)

Scaffolding installed for the Masonry work on the north side of LSI. January 2002

Click on image to enlarge (640 x 480, 61K)

Material/Personnel hoist is installed on the south side of LSI. January 2002

Click on image to enlarge (640 x 480, 64K)

Parking Structure 858' level is poured. January 2002

       
  Photos - December 2001      

Click on image to enlarge (640 x 480, 71K)

Northwest side of the Life Sciences Institute. Dec 2001

Click on image to enlarge (640 x 480, 71K)

Parking Structure 848 level. Dec 2001

Click on image to enlarge (640 x 480, 71K)

Commons Building formwork and walls. Dec 2001

Click on image to enlarge (640 x 480, 71K)

Formwork on the 20 line retaining wall along Washtenaw Avenue. Dec 2001

       
Photos - November 2001      

Click on image to enlarge (640 x 480, 71K)

The ironworker topping out ceremony.

Click on image to enlarge (640 x 480, 74K)

Concrete being poured on the 848 level of the Parking Structure.

Click on image to enlarge (640 x 480, 56K)

Strobic fans are installed on the LSI roof.

Click on image to enlarge (640 x 480, 68K)

Slab on grade being poured in the Parking Structure.

       
Photos - October 2001      

Click on image to enlarge (640 x 480, 98K)

Construction site.

Click on image to enlarge (640 x 480, 65K)

Steel for the LSI was erected while maintaining the ramp through the building for access to the Parking Structure.

Click on image to enlarge (640 x 480, 66K)

Parking Structure Foundations and Columns along B Line.

Click on image to enlarge (640 x 480, 53K)

Formwork begins on the 848 level.

     

Click on image to enlarge (640 x 480, 64K)

Walls being formed and poured for the Commons Building.

     
       

Photos - September 2001

     

Click on image to enlarge (640 x 480, 58K)

The top to the Parking Structure storm water detention basin is poured.

Click on image to enlarge (640 x 480, 66K)

North side of the Life Sciences Institute.

Click on image to enlarge (640 x 480, 69K)

Wall formwork is installed at the north end of the Commons Building.  

Click on image to enlarge (640 x 480, 64K)

Post Tensioning cables and conventional reinforcing steel installed on the detention basin lid.

       
Photos - August 2001      

 

Click on image to enlarge (412 x 308, 81K)

Structural Steel erection continues on the Life Sciences Institute.

Click on image to enlarge (520 x 390, 145K)

Concrete is poured in the storm water detention basin.

Click on image to enlarge (553 x 415, 122K)

Commons Building tunnel opening.

Click on image to enlarge (545 x 409, 114K)

Commons Building footings being formed.

       
Photos - June 2001      

Life Sciences Institute concrete foundation wall pour.

Click on image to enlarge (640 x 480 60K)

Excavation for the Commons Building.

Click on image to enlarge (640 x 480 60K)

Construction of the common wall between the Life Sciences Institute (LSI) and the Parking Structure.

Click on image to enlarge (640 x 480 59K)

Forming of the Dental Chamber foundation floor.

Click on image to enlarge (640 x 480 62K)

       
Photos - May 2001      
 

Forming and reinforcing steel for Common wall footing (between LSI and Parking Structure.)

Click on image to enlarge (640x480 69K)

A view of the site from across Washtenaw Avenue.

Click on image to enlarge (640x480 56K)

Chamber Floor Rebar.

Click on image to enlarge (640x480 60K)

 
       
Photos - April 2001      

Site Overview.

Click on image to enlarge (640x480 135K)

Murals by Ypsilanti High School students on construction fence.

Click on image to enlarge (640x480 135K)

Footing for Tower Crane No. 2.

Click on image to enlarge (640x480 135K)

Installation of Parking Structure Caisson.

Click on image to enlarge (640x480 135K)

       
Photos - March 2001      

The tower crane being erected.

Click on image to enlarge (640x480 135K)

An eight foot caisson being drilled.

Click on image to enlarge (640x480 135K)

Earth retention tie-back installation along Washtenaw Avenue.

Click on image to enlarge (640x480 135K)

Caisson drilling, view from the tower crane.

Click on image to enlarge (640x480 135K)

       
Photos - February 2001      

Concrete being poured for the tower crane foundation. February 2001

Click on image to enlarge (640x480 114K)

Earth Retention and excavation near North Hall. February 2001

Click on image to enlarge (640x480 104K)

Stone placement along Palmer Drive for Construction traffic. February 2001.

Click on image to enlarge (640x480 130K)

Sheet piling being driven along Palmer Drive. February 2001

Click on image to enlarge (640x480 103K)


Sheet pile earth retention being installed at the north west corner of the site near Plant Services and Fletcher Street Parking Structure.

Click on image to enlarge (832x624 116K)

Installation of the tie back system for the earth retention at the south end of the site near North Hall.

Click on image to enlarge (832x624 116K)

Large drop manhole for the storm water cistern being constructed at the south west corner of the site near the Dental School.

Click on image to enlarge (832x624 116K)

Relocating the underground utilities beneath Palmer Drive.

Click on image to enlarge (832x624 116K)

       
Photos - January 2001      

Siding installation on the NUBS enclosure.

Click on image to enlarge (640x406 49K)

Installation of Storm and Sanitary lines along Palmer Drive.

Click on image to enlarge (640x480 111K)

Earth retention tie-backs being installed along the Fletcher Street Parking Structure.

Click on image to enlarge (640x480 115K)

The Construction of the Central Power Plant Loading Dock.

Click on image to enlarge (640x406 96K)

       
Photos - November/December 2000      

Phase I Demolition of the North University.

Click on image to enlarge (642 x 482 86K)

Demolition of the North University Building-Phase 1, just before the snow started to fall.

Click on image to enlarge (642 x 482 81K)

Erection of the enclosed stairway at the North University Building.

Click on image to enlarge (642 x 482 93K)

The Dental Building Loading Dock Nearing Completion.

Click on image to enlarge (642 x 482 93K)


     

Installation and Backfill of the Electrical Duct Bank along Palmer Drive.

Click on image to enlarge (642 x 482 110K)

     
       
Photos - October 2000      

Sheet piling being driven along Washtenaw Avenue.

Click on image to enlarge (624 x 468 72K)

Interior demolition of the North University Building-Phase 1.

Click on image to enlarge (624 x 468 79K)

Installation of by-pass piping between the Plant Services Building and the Central Power Plant.

Click on image to enlarge (624 x 468 98K)

By-pass piping is tied-in at the Dental Building Tunnel.

Click on image to enlarge (624 x 468 120K)

     

Excavation is done for the new Dental Building Loading Dock.

Click on image to enlarge (624 x 468 92K)

     
       
Photos - September 2000      

Sheet piling being driven along Washtenaw Avenue.

Click on image to enlarge (640 x 480 119K)

Interior demolition of the North University Building-Phase 1.

Click on image to enlarge (640 x 480 122K)

Installation of by-pass piping between the Plant Services Building and the Central Power Plant.

Click on image to enlarge (624 x 468 93K)

By-pass piping is tied-in at the Dental Building Tunnel.

Click on image to enlarge (624 x 468 109K)

   

Excavation is done for the new Dental Building Loading Dock.

Click on image to enlarge (624 x 468 122K)

Excavation is done for the new Dental Building Loading Dock.

Click on image to enlarge (640 x 480 124K)

   
       
       



Aerial Photo (814x600, 197k)