| Photos - September 2002 |
|
|
|
 |
 |
 |
 |
Click on image to enlarge (640 x 480, 68K)
Windows Installed on the west elevation of the LSI Building. September
2002 |
Click on image to enlarge (640 x 480, 49K)
Cooling Towers Delivered to the Commons Building. September 2002 |
Click on image to enlarge (640 x 480, 56K)
868’ level bridge to the Fletcher deck. September 2002 |
Click on image to enlarge (640 x 480, 58K)
LSI Loading Dock (Area 3). September 2002 |
| |
|
|
|
| Photos - August 2002 |
|
|
|
 |
 |
 |
 |
Click on image to enlarge (640 x 480, 65K)
Stone placement on the west elevation of the LSI Building August 2002 |
Click on image to enlarge (640 x 480, 67K)
Hoist installed on south side of Commons Building August 2002 |
Click on image to enlarge (640 x 480, 67K)
Excavation for the LSI loading dock August 2002 |
Click on image to enlarge (640 x 480,63
67K)
Shoring and fromwork for the Fletcher bridge connector August 2002 |
| |
|
|
|
| Photos - July 2002 |
|
|
|
 |
 |
 |
 |
| Click on image to enlarge (640 x 480, 65K)
Stone placement on the LSI Building July 2002 |
Click on image to enlarge (640 x 480, 61K)
Parking Structure July 2002 |
Click on image to enlarge (640 x 480, 68K)
Level 1 raised concrete floor in the Commons Building ready for concrete
July 2002 |
Click on image to enlarge (640 x 480,63 K)
Auger cast piles for pedestrian bridge being installed July 2002
|
| |
|
|
|
| Photos - June 2002 |
|
|
|
 |
 |
 |
 |
Click on image to enlarge (640 x 480, 71K)
Installation of chillers in Commons Building June 2002 |
Click on image to enlarge (640 x 480, 56K)
Toilet room plumbing in LSI Building June 2002 |
Click on image to enlarge (640 x 480, 71K)
Lecture hall, prior to concrete, in the Commons Building June 2002 |
Click on image to enlarge (640 x 480, 60K)
Site preparation for LSI loading dock June 2002 |
| |
|
|
|
| Photos - May 2002 |
|
|
|
 |
 |
 |
 |
Click on image to enlarge (640 x 480, 75K)
NUBS demolition. May 2002 |
Click on image to enlarge (640 x 480, 59K)
Completion of structural steel for Commons Building. May 2002 |
Click on image to enlarge (640 x 480, 66K)
Post tension wires on Parking Structure. May 2002 |
Click on image to enlarge (640 x 480, 70K)
LSI mockup. May 2002 |
| |
|
|
|
| Photos - April 2002 |
|
|
|
 |
 |
 |
 |
Click on image to enlarge (640 x 480, 58K)
Permanent Utility Tunnel Tie-in. April 2002 |
Click on image to enlarge (640 x 480, 70K)
Structural steel erection of the Commons Building. April 2002 |
Click on image to enlarge (640 x 480,61K)
Concrete poured on west side of the Parking Structure. April 2002 |
Click on image to enlarge (640 x 480, 54K)
Masonry block on north and west sides of LSI. April 2002 |
| |
|
|
|
| Photos - March 2002 |
|
|
|
 |
 |
 |

|
Click on image to enlarge (640 x 480, 58K)
Electrical and toilet rooms framed on level 6. March 2002 |
Click on image to enlarge (640 x 480, 70K)
Structural steel and decking continue on the Commons Building. March
2002 |
Click on image to enlarge (640 x 480,61K)
Formwork continues on the east side of the Parking Structure. March
2002 |
Click on image to enlarge (640 x 480, 54K)
Masonry block installed on the LSI construction mock-up. March 2002 |
| |
|
|
|
| Photos - February 2002 |
|
|
|
 |
 |
 |
 |
Click on image to enlarge (640 x 480, 67K)
Air handling units delivered to the LSI Building. February 2002 |
Click on image to enlarge (640 x 480, 68K)
Decking continues on the west side of the Parking Structure. February
2002 |
Click on image to enlarge (640 x 480,78K)
Structural steel is erected in the Commons Building. February 2002 |
Click on image to enlarge (640 x 480, 59K)
Formwork on the east side of the Parking Structure. February 2002 |
| |
|
|
|
| Photos - January 2002 |
|
|
|
 |
 |
 |
 |
Click on image to enlarge (640 x 480, 62K)
Commons Building Structural Steel is erected. January 2002 |
Click on image to enlarge (640 x 480, 54K)
Scaffolding installed for the Masonry work on the north side of LSI.
January 2002 |
Click on image to enlarge (640 x 480, 61K)
Material/Personnel hoist is installed on the south side of LSI. January
2002 |
Click on image to enlarge (640 x 480, 64K)
Parking Structure 858' level is poured. January 2002 |
| |
|
|
|
| Photos - December 2001 |
|
|
|
 |
 |
 |
 |
Click on image to enlarge (640 x 480, 71K)
Northwest side of the Life Sciences Institute. Dec 2001 |
Click on image to enlarge (640 x 480, 71K)
Parking Structure 848 level. Dec 2001 |
Click on image to enlarge (640 x 480, 71K)
Commons Building formwork and walls. Dec 2001 |
Click on image to enlarge (640 x 480, 71K)
Formwork on the 20 line retaining wall along Washtenaw Avenue. Dec 2001 |
| |
|
|
|
| Photos - November 2001 |
|
|
|
 |
 |
 |
 |
Click on image to enlarge (640 x 480, 71K)
The ironworker topping out ceremony. |
Click on image to enlarge (640 x 480, 74K)
Concrete being poured on the 848 level of the Parking Structure. |
Click on image to enlarge (640 x 480, 56K)
Strobic fans are installed on the LSI roof. |
Click on image to enlarge (640 x 480, 68K)
Slab on grade being poured in the Parking Structure. |
| |
|
|
|
| Photos - October 2001 |
|
|
|
 |
 |
 |
 |
Click on image to enlarge (640 x 480, 98K)
Construction site.
|
Click on image to enlarge (640 x 480, 65K)
Steel for the LSI was erected while maintaining the ramp through the
building for access to the Parking Structure. |
Click on image to enlarge (640 x 480, 66K)
Parking Structure Foundations and Columns along B Line. |
Click on image to enlarge (640 x 480, 53K)
Formwork begins on the 848 level. |
 |
|
|
|
Click on image to enlarge (640 x 480, 64K)
Walls being formed and poured for the Commons Building. |
|
|
|
| |
|
|
|
| Photos - September 2001 |
|
|
|
 |
 |
 |
 |
Click on image to enlarge (640 x 480, 58K)
The top to the Parking Structure storm water detention basin is poured.
|
Click on image to enlarge (640 x 480, 66K)
North side of the Life Sciences Institute. |
Click on image to enlarge (640 x 480, 69K)
Wall formwork is installed at the north end of the Commons Building.
|
Click on image to enlarge (640 x 480, 64K)
Post Tensioning cables and conventional reinforcing steel installed on
the detention basin lid. |
| |
|
|
|
| Photos - August 2001 |
|
|
|
 |
 |
 |

|
Click on image to enlarge (412 x 308, 81K)
Structural Steel erection continues on the Life Sciences Institute. |
Click on image to enlarge (520 x 390, 145K)
Concrete is poured in the storm water detention basin. |
Click on image to enlarge (553 x 415, 122K)
Commons Building tunnel opening. |
Click on image to enlarge (545 x 409, 114K)
Commons Building footings being formed. |
| |
|
|
|
| Photos - June 2001 |
|
|
|
 |
 |
 |
 |
| Life Sciences Institute concrete foundation
wall pour.
Click on image to enlarge (640 x 480 60K) |
Excavation for the Commons Building.
Click on image to enlarge (640 x 480 60K) |
Construction of the common wall between
the Life Sciences Institute (LSI) and the Parking Structure.
Click on image to enlarge (640 x 480 59K) |
Forming of the Dental Chamber foundation
floor.
Click on image to enlarge (640 x 480 62K) |
| |
|
|
|
| Photos - May 2001 |
|
|
|
 |
 |
 |
|
Forming and reinforcing steel for Common
wall footing (between LSI and Parking Structure.)
Click on image to enlarge (640x480 69K) |
A view of the site from across Washtenaw
Avenue.
Click on image to enlarge (640x480 56K) |
Chamber Floor Rebar.
Click on image to enlarge (640x480 60K) |
|
| |
|
|
|
| Photos - April 2001 |
|
|
|
 |
 |
 |
 |
|
Site Overview.
Click on image to enlarge (640x480 135K) |
Murals by Ypsilanti High School students on construction fence.
Click on image to enlarge (640x480 135K) |
Footing for Tower Crane No. 2.
Click on image to enlarge (640x480 135K) |
Installation of Parking Structure Caisson.
Click on image to enlarge (640x480 135K) |
| |
|
|
|
| Photos - March 2001 |
|
|
|
 |
|
 |
 |
|
The tower crane being erected.
Click on image to enlarge (640x480 135K) |
An eight foot caisson being drilled.
Click on image to enlarge (640x480 135K) |
Earth retention tie-back installation along Washtenaw Avenue.
Click on image to enlarge (640x480 135K) |
Caisson drilling, view from the tower crane.
Click on image to enlarge (640x480 135K) |
| |
|
|
|
| Photos - February 2001 |
|
|
|
 |
 |
 |
 |
|
Concrete being poured for the tower crane foundation. February 2001
Click on image to enlarge (640x480 114K) |
Earth Retention and excavation near North Hall. February 2001
Click on image to enlarge (640x480 104K) |
Stone placement along Palmer Drive for Construction traffic. February
2001.
Click on image to enlarge (640x480 130K) |
Sheet piling being driven along Palmer Drive.
February 2001
Click on image to enlarge (640x480 103K) |
 |
 |
 |

|
Sheet pile earth retention being installed
at the north west corner of the site near Plant Services and Fletcher
Street Parking Structure.
Click on image to enlarge (832x624 116K) |
Installation of the tie back system for the
earth retention at the south end of the site near North Hall.
Click on image to enlarge (832x624 116K) |
Large drop manhole for the storm water cistern
being constructed at the south west corner of the site near the Dental
School.
Click on image to enlarge (832x624 116K) |
Relocating the underground utilities beneath
Palmer Drive.
Click on image to enlarge (832x624 116K) |
| |
|
|
|
| Photos - January 2001 |
|
|
|
 |
 |
 |
 |
|
Siding installation on the NUBS enclosure.
Click on image to enlarge (640x406 49K) |
Installation of Storm and Sanitary lines along Palmer Drive.
Click on image to enlarge (640x480 111K) |
Earth retention tie-backs being installed along the Fletcher Street
Parking Structure.
Click on image to enlarge (640x480 115K) |
The Construction of the Central Power Plant
Loading Dock.
Click on image to enlarge (640x406 96K) |
| |
|
|
|
| Photos - November/December 2000 |
|
|
|
 |
 |
 |
 |
|
Phase I Demolition of the North University.
Click on image to enlarge (642 x 482 86K) |
Demolition of the North University Building-Phase
1, just before the snow started to fall.
Click on image to enlarge (642 x 482 81K) |
Erection of the enclosed stairway at the
North University Building.
Click on image to enlarge (642 x 482 93K) |
The Dental Building Loading Dock Nearing Completion.
Click on image to enlarge (642 x 482 93K) |

|
|
|
|
|
Installation and Backfill of the Electrical Duct Bank along Palmer
Drive.
Click on image to enlarge (642 x 482 110K)
|
|
|
|
| |
|
|
|
| Photos - October 2000 |
|
|
|
 |
 |
 |
 |
|
Sheet piling being driven along Washtenaw Avenue.
Click on image to enlarge (624 x 468 72K) |
Interior demolition of the North University
Building-Phase 1.
Click on image to enlarge (624 x 468 79K) |
Installation of by-pass piping between the Plant Services Building and
the Central Power Plant.
Click on image to enlarge (624 x 468 98K) |
By-pass piping is tied-in at the Dental Building
Tunnel.
Click on image to enlarge (624 x 468 120K) |
 |
|
|
|
Excavation is done for the new Dental Building
Loading Dock.
Click on image to enlarge (624 x 468 92K) |
|
|
|
| |
|
|
|
| Photos - September 2000 |
|
|
|
 |
 |
 |
 |
|
Sheet piling being driven along Washtenaw Avenue.
Click on image to enlarge (640 x 480 119K)
|
Interior demolition of the North University
Building-Phase 1.
Click on image to enlarge (640 x 480 122K) |
Installation of by-pass piping between the
Plant Services Building and the Central Power Plant.
Click on image to enlarge (624 x 468 93K) |
By-pass piping is tied-in at the Dental Building
Tunnel.
Click on image to enlarge (624 x 468 109K)
|
 |
|
|
|
Excavation is done for the new Dental Building
Loading Dock.
Click on image to enlarge (624 x 468 122K) |
Excavation is done for the new Dental Building Loading
Dock.
Click on image to enlarge (640 x 480 124K) |
|
|
| |
|
|
|
| |
|
|
|