| September 2005 |
|
|
|
 |
 |
 |
 |
| Women's room |
Ramp to toilet rooms |
South Wall |
Events area looking north |
 |
 |
 |
|
| Piping installed at air-handler |
New cable routing |
Facade view |
|
| August 2005 |
|
|
|
 |
 |
 |
 |
| Team cookout on the Mortenson Family Plaza |
Plaza pavers complete, looking northeast |
New paving on Stadium Concourse |
New dumpster enclosure |
 |
 |
 |
|
| Nearly completed facade |
Masons installing the M |
Crisler sidewalk replacement |
|
July 2005 |
|
|
|
|
|
|
|
Events space looking southwest
|
Brick parapet and peastone paver base
|
New fence posts and waterproofing
|
Waterproofing nearly completed
|
|
|
|
|
Starting brick at parpet wall
|
Site overview looking east
|
New cooling unit
|
Toilet room wall layout
|
June 2005 |
|
|
|
|
|
|
|
Crisler concourse decking |
Masonry parapet wall installed |
New Crisler concourse slab |
Prepped to place Plaza concrete |
|
|
|
|
Plaza deck and wall pre-waterproofing |
New stair framing |
New steel framing in Crisler |
Underslab plumbing at new toilet rooms |
May 2005 |
|
|
|
|
|
|
|
| Deck with stud bolts |
Decking ready for installation |
First lift of waterproofing |
Framing through receiving door |
 |
 |
 |
 |
| Lobby area looking south |
Steel and deck complete |
Steel erection |
View from the west |
| April 2005 |
|
|
|
 |
 |
 |
 |
| Crisler mass excavation complete |
Wall forms |
Excavating inside Crisler |
Footings at new receiving door |
 |
 |
|
|
| New concrete wall |
Wall footings |
|
|
| March 2005 |
|
|
|
|
|
|
|
New raceways for power feeds |
Temporary partition wall |
Trophy case demolition |
Tunnel demolition |
|
|
|
|
Crisler foundations after tunnel demolition |
Debris from tunnel |
Excavating to grade |
|
| February 2005 |
|
|
|
 |
 |
 |
.jpg) |
| Crisler foundations exposed by excavation
|
Excavation and demolition |
Excavation |
New telecom conduits to Crisler (north) |
| |
|
|
|