Joan and Sanford Weill Hall-Gerald R. Ford School of Public Policy
Project Data
Project Number:
P100510102001
Budget:
$35
million
Schedule:
Estimated
Construction Start: November 2004
Estimated
Construction Completion: June 2006
Square Ft.:
80,000
gross sq. ft.
Project Team
Design Team:
Robert
A. M. Stern Architects
Albert Kahn Associates
Construction Team:
Clark Construction Company
Owner Team:
Project
Lead:
 Architecture, Engineering and Construction
Support
Units:
 Occupational
Safety and Environmental Health
 Plant
Operations
 Gerald
R. Ford School of Public Policy
Last
modified:
Thursday March 09 2006