Project Data
Project Number:
P1001694-98-001
Budget:
$
35.6 million
Schedule:
Estimated
Construction Start: October 1999
Estimated
Construction Completion: November 2001
Square Ft.:
177,400 gross sq. ft.
Project Team
Partnering
Design Team:
Architect/Engineer:
SSOE, Inc.
Landscape
Architect: JJR
Construction Team:
Sorensen
Gross Construction Co., Inc.
Owner Team:
Project Lead:
 Architecture, Engineering and Construction
Support
Units Ann Arbor Campus:
 Occupational
Safety and Environmental Health
 Plant
Operations
Support
Units Flint Campus:
 Flint
Facilities Management
 Flint
Environmental, Health and Safety Department
 Flint
Purchasing Department
 Flint
Information Technology Services
 Flint
Department of Public Safety
|