Dearborn Science Building Addition

Project Data

Project Number:
P100513804001

Budget:
$9.6 million

Schedule:
Estimated Construction Start: September 2004
Estimated Construction Completion: May 2006
Square Ft.:
29,000 gross sq. ft.

Project Team

Design Team:
The Stubbins Associates, Inc.

Construction Team:
White Construction

Owner Team:
Project Lead:
Architecture, Engineering and Construction
Support Units:
University of Michigan Dearborn
University of Michigan Dearborn Services
University of Michigan Dearborn Campus Safety