Dearborn Engineering Building Addition
Project Data
Project Number:
P100513704002
Budget:
$12.6
million
Schedule:
Estimated
Construction Start: August 2004
Estimated
Construction Completion: April 2006
Square Ft.:
46,000
gross sq. ft.
Project Team
Design Team:
Lord Aeck Sargent
Construction Team:
JM Olson Corporation
Owner Team:
Project
Lead:
 Architecture, Engineering and Construction
Support
Units:
 University of Michigan Dearborn
 University of Michigan Dearborn Services
 University of Michigan Dearborn Campus Safety
Last
modified:
Tuesday September 05 2006
University of Michigan - Architecture, Engineering and Construction
A326 East Hoover Ann Arbor MI 48109-1002
© 2008 The Regents
of the University of Michigan
|