The University of Michigan Home Page

Project Overview

Project Data

Design

Photos/3D

Web Cam

Monthly Updates (PDF)

Location of Project

Regents Items

Informative Links

Major Projects

HOME

Computer Science and Engineering Building

Photos - Click on the image for a larger photo.
June 2005      

June 27, 2005 – West Elevation

June 27, 2005 –Atrium Skylight Soffits

June 27, 2005 - Southeast Elevation

June 27, 2005 - Northeast Elevation
May 2005      

May 31, 2005 – Backfill in Courtyard

May 31, 2005 – Drywall at Atrium Ceiling

May 31, 2005 - Southeast Elevation

May 31, 2005 - Northeast Elevation
April 2005      
May 4, 2005 - Atrium Skylight Soffits

May 4, 2005 - Atrium Scaffolding

May 4, 2005 - Southeast Elevation

May 4, 2005 - Northeast Elevation

March 2005      

Fire Pump

Drywall at Third Floor Offices

Southeast Elevation

Northeast Elevation
February 2005

Skylight and Penthouse Metal Panel Installation

120 Seat Classroom Ductwork

Northeast Elevation

South Elevation

January 2005

Penthouse Air Handling Unit

Electrical Substation

Northeast Elevation

South Elevation

December 2004 

West Side of Atrium

West Elevation

Northeast Elevation

South Elevation

November 2004

Shaft No. 1 Ductwork

West Elevation

Northeast Elevation

South Elevation

October 2004
Third Floor Corridor Wall

West Elevation

North Elevation Precast

South Elevation Precast

September 2004

South Elevation of the Building

Concrete Slab on Deck Installation on the North Half Underway

Roof Parapet Construction

Precast Fins at the North Elevation

August 2004
Architectural Concrete Wall at Ramp
First Floor Corridor Facing the Dow Building

Third Floor Slab Branch Power Rough-ins

Structural Steel at Atrium from the South
July 2004

North Structural Steel from Southwest

North Structural Steel from Northwest

Foundations for Structural Steel on the South Half of the Building

Structural Steel Erection Underway on South Half of the Building

June 2004
Excavations at North Wall of First Floor June 2004
North Concrete Wall of First Floor June 2004
Initial Structural Steel Erection June 2004

Third and Fourth Floor Structural Steel North of E-Line June 2004

May 2004

Elevator No. 1 Foundation

Formwork at Stair #2 at the Dow Building

Second Floor Concrete Foundaitons and Walls

Concrete Wall at Dow Mechanical Room
April 2004

Reinforicng Steel Installation

Completed Foundation Wall

Foundation for Stair No. 1

Backfilling Foundations at the North Side

March 2004      
 
Incoming Primary Power Ductbank Installation Stepped Footing Installation Excavation for Concrete Mass Footing  
February 2004      
 
Storm Sewer Piping and Structures at the North Side of the Site is Underway Crane Mobilized for Foundation Work Brick Mock Up Panels for Two (2) Brick Selections Under Consideration  
January 2004      
 
College of Engineering Project Control Center Dow Building Basement Exposed Rough Grade at Dow Building  

Last modified: Thursday March 09 2006  


University of Michigan - Architecture, Engineering and Construction
A326 East Hoover   Ann Arbor MI 48109-1002  

© 2009 The Regents of the University of Michigan