Project Data
Project Number:
P100503700001
Budget:
$220
million + inflation
Schedule:
Construction Start: October 2001
Construction Completion: December 2005
Square Ft.:
472,000 gross sq. ft.
Project Team
Design Team:
Polshek
Partnership
Construction Team:
Gilbane
Building Company/Clark
Construction Company
Owner Team:
Project
Lead:
 Architecture, Engineering and Construction
Support
Units:
 Occupational
Safety and Environmental Health
 Plant
Operations
 Medical
School
 Unit
for Laboratory Animal Medicine
Related Projects
BSRB Chiller Plant
BSRB Utilities Relocation and Excavation Package
Medical School Animal Facilities and Demolition of the Neuroscience Building
|