East Ann Arbor Ambulatory Surgery and Medical Procedures Center

Project Data

Project Number:
P100503804001

Budget:
$30 million

Schedule:
Estimated Construction Start: October 2004
Estimated Construction Completion:December 2005
Square Ft.:
46,000 gross sq. ft.

Project Team

Design Team:
Albert Kahn Associates

Construction Team:
Turner Construction Company

Owner Team:
Project Lead:
Architecture, Engineering and Construction
Support Units:
Occupational Safety and Environmental Health
Plant Operations