| July 2006 |
|
|
|
|
 |
 |
 |
 |
 |
July 31, 2006 – Southeast Elevation |
July 31, 2006 – ATL Lobby |
July 31, 2006 – CAEN Lab 1310 |
July 31, 2006 – Classroom 1123 |
July 31, 2006 – Wet Lab 1220 |
 |
|
|
|
|
July 31, 2006 – Dry Lab 1105 |
|
|
|
|
| June 2006 |
|
|
|
|
 |
 |
 |
 |
 |
June 30, 2006 - Southeast Elevation |
June 30, 2006 – Corridor 2C16 |
June 30, 2006 – Dry Lab 1105 |
June 30, 2006 – Kitchen in Room 2251 |
June 30, 2006 – Wet Lab 1210 |
 |
|
|
|
|
June 30, 2006 – Corridor 1C12 |
|
|
|
|
| May 2006 |
|
|
|
|
 |
 |
 |
 |
 |
May 31, 2006 - Southeast Elevation |
May 31, 2006 – Corridor 2C16 |
May 31, 2006 – Cable Tray in Corridor 1C14 |
May 31, 2006 – Millwork in Room 2153 |
May 31, 2006 – Wet Lab 1210 |
 |
|
|
|
|
May 31, 2006 – Dry Lab 1105 |
|
|
|
|
June 2005 |
|
|
|
|
|
|
|
|
|
June 30, 2005 – Southeast Elevation |
June 30, 2005 – East Elevation |
June 30, 2005 – Southwest Elevation |
June 9, 2005 – Switchgear Room Looking North |
June 9, 2005 – Boiler Room Looking East |
May 2005 |
|
|
|
|
|
|
|
|
|
May 31, 2005 – Southeast Elevation |
May 31, 2005 - Southwest Elevation |
May 31, 2005 - First Floor Looking South |
May 31, 2005 – Lobby Area from Second Floor |
May 31, 2005 – Second Floor West Wall Looking South |
April 2005 |
|
|
|
|
|
|
|
|
|
May 4, 2005 - East Elevation |
May 4, 2005 - Southwest Elevation |
May 4, 2005 - First Floor Looking North |
May 4, 2005 – Second Floor Looking North |
|
March 2005 |
|
|
|
|
|
|
|
|
|
East Elevation |
South Elevation |
Second Floor Looking North |
Lobby Stairs |
|
February 2005 |
|
|
|
|
|
|
|
|
|
East Elevation |
South Elevation |
Entrance with Canopy and Sunscreen |
Second Floor Looking North |
|
| January 2005 |
|
|
|
|
 |
 |
 |
 |
|
| East Elevation |
South Elevation |
Forming Equipment Pads |
Second Floor Looking South |
|
| December 2004 |
|
|
|
|
 |
 |
 |
 |
|
| East Elevation |
South Elevation Looking North |
South West Elevation |
Metal Shingles on North Elevation |
|
| November 2004 |
|
|
|
|
 |
 |
 |
 |
|
Metal Shingle Installation on the North Elevation |
West Elevation |
East Elevation |
South Elevation Looking North |
|
| October 2004 |
|
|
|
|
 |
 |
 |
 |
|
West Elevation with Masonry Installation |
South Elevation with Masonry Installation |
Steel Erection of Canopy |
South Elevation at Lobby Area |
|
| September 2004 |
|
|
|
|
 |
 |
 |
 |
|
Triangle Portion Looking North |
West Elevation with Exterior Stud Wall Installation |
East Elevation |
East Elevation |
|
| August 2004 |
|
|
|
|
 |
 |
 |
 |
|
Second Floor Elevated
Slab |
Steel Erection of Triangular Portion of Building |
Steel Deck at Penthouse Level |
Second Floor Elevated Slab Reinforcement |
|
| July 2004 |
|
|
|
|
 |
 |
 |
 |
|
Steel Erection with Partial Decking |
Steel column line looking toward existing building |
Structural Steel with Metal Deck |
Steel Erection at South end of Building |
|
| June 2004 |
|
|
|
|
 |
 |
 |
 |
|
Steel Erection at Interface with Existing Building June 2004 |
Steel at Existing Building from the South June 2004 |
Steel at Existing Building from the Southwest June 2004 |
Steel Lay Down June 2004 |
|
| May 2004 |
|
|
|
|
 |
 |
 |
 |
|
Foundation at Northeast Corner from ATL Roof |
Foundation at Northeast Corner from ATL Roof |
Foundation for West Wall |
Foundation for East Wall |
|
| April 2004 |
|
|
|
|
 |
 |
 |
 |
|
Foundations in Progress |
Building Pad with Grade Beams |
Foundations in Progress |
Forming for Foundations |
|
| March 2004 |
|
|
|
|
 |
 |
 |
 |
|
| Sanitary Piping in Progress |
Building Pad is Complete |
Connection to Storm Structure |
Site Construction Fence Relocated |
|
| February 2004 |
|
|
|
|
 |
 |
 |
|
|
Building Pad in Process |
Construction Fence in Place |
Site Clearing Underway |
|
|
| |
|
|
|
|
| |
|
|
|
|
| |
|
|
|
|
| |
|
|
|
|
| |
|
|
|
|
| |
|
|
|
|
| |
|
|
|
|